ProjectLinklaters Global Headquarters 2024 – 2025SectorCommercial / Legal / Corporate Office
Location20 Ropemaker Street, LondonBuilding Size360,000 sq ft
Delivery PartnerPhoenix MEFloors17
Enviro RoleMEP commissioning managementProject TypeLandmark office fit out
End UserLinklatersKey Output1,500+ ATPs managed and issued

Project Overview

Linklaters has unveiled its new global headquarters at 20 Ropemaker Street in London, a 360,000 sq ft landmark development in the City designed to support teamwork, collaboration and high-performance working. The office spans 17 floors and includes state-of-the-art facilities such as collaborative workspaces, a fitness centre, yoga and spin studios, high-specification events space, roof terraces and balconies, and a terrace café with views across the City. The development also includes more than 500 cycle storage spaces and a dedicated active commuter entrance, supporting a modern and sustainable workplace experience.

The Challenge

As a major headquarters fit out with extensive building services, specialist facilities and multiple integrated systems, Linklaters required a highly coordinated commissioning management approach. The project involved mechanical, electrical, security and fire services, alongside critical systems serving data rooms, event spaces and workplace environments. With a large volume of ATPs to manage and integrated testing requirements across multiple disciplines, clear control, technical oversight and structured coordination were essential to successful delivery. ENVIRO was appointed by Phoenix ME to provide MEP commissioning management support and became a crucial part of the project delivery team.

Our Approach

ENVIRO provided full MEP commissioning management across the project, coordinating activity across electrical, mechanical, security and fire services. The team managed commissioning progress, coordinated testing requirements, supported system readiness and led integrated testing activities. A key part of the approach was maintaining control of documentation, ATP management and sign-off, ensuring commissioning records were progressed in line with project requirements. With more than 1,500 ATPs successfully managed and issued, ENVIRO supported the project team through an intense and technically demanding commissioning programme.

Key Services Delivered

  • MEP commissioning management
  • Mechanical commissioning coordination
  • Electrical commissioning coordination
  • Security systems commissioning management
  • Fire services commissioning management
  • Integrated testing leadership
  • ATP management and issue
  • Documentation review and coordination
  • Heat-load testing management
  • Domestic water commissioning and balancing
  • CPC water treatment management
  • BMS commissioning coordination
  • Support through project close-out and handover

Objective

The new Linklaters headquarters has been designed with a strong focus on sustainability, workplace wellbeing and environmental performance. The fit out incorporates sustainable design practices, including zero waste to landfill, efficient use of energy and water, and engagement with suppliers around product and material environmental performance. The project’s facilities, including fitness areas, event spaces, roof terraces and active commuter infrastructure, created a varied and technically complex commissioning environment requiring coordination across multiple systems and end-use spaces.

Results

ENVIRO played a key role in supporting the successful commissioning delivery of Linklaters’ new global headquarters. The team managed and issued more than 1,500 ATPs, led integrated testing activities and maintained commissioning control across mechanical, electrical, security and fire services. Through structured MEP commissioning management, ENVIRO helped support the delivery of a high-profile, technically complex headquarters fit out for one of the world’s leading law firms.

Systems managed by ENVIRO:

  • LTHW systems
  • CHW systems
  • Critical CHW systems
  • Ventilation systems
  • CPC water treatment
  • Domestic water commissioning
  • Domestic water balancing
  • Heat-load testing of data rooms and event spaces
  • BMS
  • LV small power
  • Resilient power controls
  • Data and network systems
  • Security systems
  • Fire-fighting network
  • Cause and Effect management

Deliver your next project with confidence

ENVIRO provides specialist commissioning management and validation support for complex construction projects, helping teams manage risk, maintain compliance and keep progress moving.helping teams manage risk, maintain compliance and keep progress moving.

Related Services

Commissioning Management Services

Commissioning & Water Treatment Validation Services

Compliance & Risk Assessments